+86 10 85323436
Current location: Home > Reference > Nanjing Jiangbei OFMSW Project


Nanjing Jiangbei OFMSW Treatment Project


Introduction for the environmental park:

  OFMSW:73,000 t/a

  RSW:146,000 t/a

    Waste Oil:18,250 t/a

  Total ocupation is 219 Mu,including pretreatment for OFMSW and RSW, dry AD for OFMSW and wet AD for RSW.

     Project owner: Nanjing environment construction group

   Start-up time: 2018

GBE service scope:

        Dry AD: 2 sets of PF1800 steel digester

        Dewater equipment:2 sets of vibrate dewatering

      Income capacity: 73,000 t/a(OFMSW)

    Biogas production: 6,700,000 Nm³/a

        CO2 saving: 12,000 t/a